Section 3: Indiana
7/12/23: The Indiana Department of Transportation has advertised I-69 ORX Section 3 for a special letting on November 1, 2023. Click here to learn more. Find additional information from INDOT here.
An Industry Forum event was held April 13 in Evansville to share project information with contractors, suppliers, consultants, DBEs and others. Click here to review materials.
I-69 ORX Section 3 includes part of the approach roadways and bridges in Indiana that will provide all-weather construction access to the river for the future Section 2 project.
The Section 2 project will complete any roadways and bridges in Indiana that are not constructed under the Section 3 project.
The design-build project is expected to let in 2023 with construction expected to begin in 2024 and be complete in 2026.
SECTION 3 FAQs
Section 3 is nearly all Ohio River floodplain and will include construction of two small embankment sections, one near the IN/KY state line at the end of the Ohio River bridge in Section 2 and one near the existing I-69/Veterans Memorial Parkway.
Viaduct bridges will be constructed between the two short embankment sections and to connect the northerly embankment section with existing I-69 just west of Weinbach Avenue.
A new interchange will also be constructed at I-69/Veterans Memorial Parkway, providing free-flow movements in all directions.
I-69 ORX Section 3 has been funded through a $200 million investment by Indiana that was announced by Governor Holcomb in 2021.
The design build project is expected to be let in 2023. Construction is expected to begin in 2024 and to be complete in 2026.
Construction is expected to take about three construction seasons and is expected to be complete in 2026.